Tanda Thermal Power Expansion Project   
Project Code 6000003211
Project Name Tanda Thermal Power Expansion Project
Project Type Capital Project Status Active
Sector Power Project Stage Construction
Project Cost Rs. 9,188.98 Cr.   Project Phase Erection & Installation
NIC Subcode(s) Description
35102 Electric power generation by coal based thermal power plants
Facility Name Tanda Thermal Power Station Status Running 
Sector Power Main Energy Source Coal  
Commissioning Date 01-1988  Other Energy Sources Water, Fuel Oil  
Address NTPC Limited, Tanda Thermal Power Plant, Administrative Building, P.O.: Vidyut Nagar,
Ambedkar Nagar, Uttar Pradesh
224238, India
Telephone 05273-292331
Fax 05273-284189
Owner National Thermal Power Corporation Limited National Thermal Power Corporation Limited Website http://www.ntpc.co.in/
Operator National Thermal Power Corporation Limited National Thermal Power Corporation Limited Website http://www.ntpc.co.in/
Unit Name Unit Status Unit Category Commissioning Date
Unit-6 (Tanda TPP) Unit-6 (Tanda TPP) Construction Steam driven 05-2019
Unit-5 (Tanda TPP) Unit-5 (Tanda TPP) Construction Steam driven 11-2018
Company Name Company Classification
Larsen & Toubro Limited Contractor
Bharat Heavy Electricals Ltd. Contractor

National Thermal Power Corporation Limited plans to commission one of the 660 MW units till December 2018 out of its ongoing 1320 MW (2x660 MW) super-critical thermal power expansion project at its existing facility of 440MW at Tanda Thermal Power Station. The other unit is expected to be commissioned in mid-2019. Tender documents are now getting prepared for the implementation of an FGD. Further bids are expected soon. The project requirement are: absorber system, gas to gas heat exchanger, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, slurry re-circulation pumps, oxidation blower, gypsum bleed pumps, limestone grinding system, limestone slurry pumps, vacuum belt filter system, auxiliary absorbent slurry pumps with drive motor, piping, valves, auxiliary absorbent tanks, limestone storage tank, limestone silos, process water storage and pumping system, booster fans, ducting, dampers along with supports, slurry piping along with associated valves, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, cooling water tank, process water tank, emergency slurry tank, among others.

RFQ for a flue gas desulphurization system is expected in October 2018, instead of June 2018.

Expenditure Approval RFQ Date Release Date Start Date Completion Date Audit Date
Sep/2014 Oct/2018 Oct/2018 Oct/2015 Q2:2019 18/May/2019
Sell Electricity?
Buy Fuel? Fuel Name Diesel
Name Project Role Designation Company City Phone Audit Date E-mail
Mr.K. S. Rajeev Owner Group General Manager (Project) National Thermal Power Corporation Limited National Thermal Power Corporation Limited Ambedkar Nagar 05273 - 281198 18/05/2019 ksrajeev@ntpc.co.in
Equipments
Category Additional Details
Environmental
  • Scrubber
  • Flue-Gas Desulfurization(FGD)
  • Filters
Structural
  • Piling
  • Frame
  • Elevators
  • Cranes
Insulation/coating
  • Insulation

Engineering Services
  • Structural
Contracting Services
  • Environmental