West Bengal Power Development Corporation Limited (WBPDCL) along with EPC contractor BHEL is developing a 660 MW super-critical thermal power expansion complex at its existing facility of 1600 MW thermal power plant (2x300 + 2x500 MW) situated in the district Murshidabad, West Bengal. EPC contractor BHEL has supplied the SG, its auxiliary, and Turbine Generator units. BHEL was also selected as an EPC contractor for FGD. Civil works have been completed for BTG and ESP units. Erection and installation of BTG pressure parts and their auxiliary are in progress. Erection works of pressure parts have been delayed due to the slow mobilization of equipment at the site. MacawberBeekey Pvt. Ltd. is constructing AHP. CHP package contractor Bengal Tools and ThyssenKrupp is building a conveyor system and WagonTripler works. BHEL has selected RB electrical as a sub-contractor for the switchyard package. Bid evaluation is in progress for the absorber system works. Preparation of tender is in progress for the limestone and gypsum handling plant.
Further bids are expected soon. Project requirements are rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.
21/03/2024
West Bengal Power Development Corporation Ltd. (WBPDCL) plans to develop a 660 MW super-critical thermal power expansion project in Murshidabad district, West Bengal. EPC contractor BHEL has supplied the BTG units and their auxiliary. Macawber Beekay Pvt. Ltd. is constructing the AHP system. ThyssenKrupp is building a conveyor system and Wagon Tippler system for CHP. RB Electrical appointed as a sub-contractor for the switchyard works. Cooling tower construction work is undergoes. ISGEC awarded for absorber system package. RITES Ltd has been appointed as a PMC for railway siding works. A tender for Twin Wagon Tippler package has been floated. Preparation of the tender is yet to be started for the railway siding system (package-5). Further bids are expected soon. Project requirements are rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.
05/01/2024
West Bengal Power Development Corporation Ltd. (WBPDCL) plans to develop a 660 MW super-critical thermal power expansion project in Murshidabad district, West Bengal. EPC contractor BHEL has supplied the BTG units and their auxiliary. Bid evaluation is in progress for the erection and installation of pressure parts. Macawber Beekay Pvt. Ltd. is constructing the AHP system. ThyssenKrupp is building a conveyor system and Wagon Tippler system for CHP. RB Electrical appointed as a sub-contractor for the switchyard works. Cooling tower construction work is undergoes. ISGEC awarded absorber system package. A tender has been floated for the ball mill system package. RITES Ltd has been appointed as a PMC for the railway siding works. Preparation of the tender is in progress for the Twin Wagon Tippler package for railway siding works. Further bids are expected soon. Project requirements are rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.
06/12/2023
West Bengal Power Development Corporation Ltd. (WBPDCL) plans to develop a 660 MW super-critical thermal power expansion project in Murshidabad district, West Bengal. EPC contractor BHEL has supplied the BTG units and their auxiliary. BHEL has floated a fresh tender for the erection and installation of pressure parts. Macawber Beekay Pvt. Ltd. is constructing the AHP system. ThyssenKrupp is building a conveyor system and WagonTripler works. RB Electrical appointed as a sub-contractor for the switchyard works. ISGEC has been selected as the absorber system contractor. Preparation of the tender has been completed for the ball mill system and it is yet to be approved. Further bids are expected soon. Project requirements are rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.
12/07/2023
West Bengal Power Development Corporation Ltd. (WBPDCL) plans to develop a 660 MW super-critical thermal power expansion project in the district Murshidabad, West Bengal. EPC contractor BHEL has supplied the BTG units and their auxiliary. Erection and installation of BTG pressure parts and their auxiliary are in progress. The erection and installation of pressure parts have been delayed due to the slow mobilization of equipment at the site. Macawber Beekay Pvt. Ltd. is constructing the AHP. CHP package contractor Bengal Tools and ThyssenKrupp is building a conveyor system and WagonTripler works. RB electrical is involved as a sub-contractor for the switchyard works. ISGEC has been selected as the absorber system contractor. Pilling and foundation works have been completed for the FGD. Structural works are in progress for FGD works. Preparation of tender is in progress for the ball mill system package and its specification finalization has been completed.
Further bids are expected soon. Project requirements are rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.
14/10/2022
West Bengal Power Development Corporation Limited (WBPDCL) has selected BHEL as an EPC package contractor in a 660 MW super-critical thermal power expansion complex at its existing facility of 1600 MW thermal power plant (2x300 + 2x500 MW) situated in the district Murshidabad, West Bengal. EPC contractor BHEL will supply the SG, its auxiliary, and Turbine Generator units. The owner has also awarded M/S BHEL as an EPC contractor for FGD, and SCR packages. Civil works have been completed for BTG and ESP units. Erection and installation of the switchyard package are in progress.AHP package was awarded to M/S MacawberBeekey Pvt. Ltd. CHP package was awarded to M/s Bengal Tools for the conveyer system and M/s ThyssenKrupp was selected for the WagonTripler package. M/s. MacawberBeekey Pvt. Ltd. has been selected as a sub-contractor for AHP. Erection and installation of pressure parts are in progress for BTG. BHEL has selected RB electrical as a sub-contractor for the switchyard package. Erection works of pressure parts have been delayed due to the slow mobilization of equipment at the site. Site preparation has been completed and the erection of the DeNox system is in progress. The preparation of the tender is in progress for the absorber system package and its specification finalization has been completed. Further bids are expected soon. Project requirements are: steam generator and its auxiliaries, steam turbine, super-critical boiler, water-cooled condenser, air preheater, vacuum pumps, boiler feed pumps, and its drives, feed pump motor, deaerating heater and closed heaters, condensate extraction pumps, suction basket strainer, furnace system, furnace chamber, air supply, and distribution system, soot blowing system, ESP, chimney (275 m), ash handling system, water treatment plant, DM plant, fire fighting system, turbine oil purification system, switch-yard equipment, cranes, Thermomechanically, treated steel, DG sets, rolling shutters, fencing materials, down shop lead (DSL) crane, carbon steel and pipe, Cu Ni / Al bronze tubes, stacker cum reclaimer, wagon tippler, piles, reinforced steel, structural steel, MS & Electro forged gratings, conveyor belts, side arm charger, dozers. Absorber system, gas-gas heater, spray headers and nozzles, mist eliminators & washing, agitators, quenching spray system, limestone grinding system, vacuum belt filter system, booster fans, ducting, low height wet chimney, FGD control room, dozers, wet ball mills, bucket elevator, gypsum dehydration, piles, spray headers, pumps (gypsum bleed, limestone slurry, auxiliary absorbent slurry with drive motor), tanks (absorbent, limestone storage, cooling water, process water, emergency slurry), silos, among others.