Department Of Water Resources, Odisha has plans to build an 18 MW (2x4 2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village in the Nabarangpur district of Odisha. AFC India Limited has completed the preparation of the SIA report. WAPCOS has prepared the DPR. The hydrology report was accorded by the CWC. EC for the project has been approved by the MoEF. The forest clearance stage -1 has been granted by DFO but the stage is in progress at the nodal office. Construction of the approach road has been completed. The project envisages the construction of an 87 m high and 3682 m long earthen dam across the Tel river. The interstate boundary with Chhattisgarh state is a major issue in the project. After several meetings, the issue has been resolved. The civil works contractors Patel Engineering have completed the mobilization of equipment at the site. Excavation works are in progress. Civil works package Lot-2 was awarded to HES Infra. and mobilization of equipment is in progress by civil works (lot-2) contractors. The tender has been floated for the hydro-mechanical works and its pre-bid meeting conducted soon. Preparation of tender is in progress for the electromechanical works and its specification finalization is in progress. Further bids are expected soon. The project requirement are load cum excavator, hydraulic excavator, dumpers, jack hammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, DG sets, bending and cutting machine, fuel/water tankers, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, actuation system, flap gates, Francis turbine, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, generator and its control panel, guide bearings, protection relays, transformer and its auxiliaries, lightning arrester panels, excitation system and its auxiliaries, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear and its auxiliaries - circuit breakers, isolators, capacitor bank, dis-connectors, governor panel, cables, transmission lines, nozzles, among others.
27/02/2024
Department Of Water Resources, Odisha plans to build an 18 MW (2x4 +2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village, Nabarangpur district, Odisha. AFC India Ltd has prepared the SIA report. WAPCOS has prepared the DPR. EC and FC have been granted. The civil work (Lot-1) contractor Patel Engineering is constructing HRT. Civil work (Lot-2) contractor HES Infra. has started the construction work. Bid evaluation is in progress for the hydro-mechanical work. Preparation of the electro-mechanical (EM) package tender has been completed and it is under approval stage. Further bids are expected soon. The project requirement is a load cum excavator, hydraulic excavator, dumpers, jackhammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, flap gates, Francis turbine, alternator, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, protection relays, transformer, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear, cables, nozzles, among others.
01/11/2023
Department Of Water Resources, Odisha plans to build an 18 MW (2x4 +2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village in the Nabarangpur district of Odisha. AFC India Ltd has prepared the SIA report. WAPCOS has prepared the DPR. EC and FC have been granted. Construction of the approach road has been completed. The interstate boundary issue with Chhattisgarh state has been resolved. The civil works contractor Patel Engineering is constructing HRT. Civil works (Lot-2) contractor HES Infra. has started the construction works. Bid evaluation is in progress for the hydro-mechanical works. Preparation of the tender has been completed for the electro-mechanical (EM) works and it is under approval stage. Further bids are expected soon. The project requirement is a load cum excavator, hydraulic excavator, dumpers, jackhammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, flap gates, Francis turbine, alternator, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, protection relays, transformer, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear, cables, nozzles, among others.
30/03/2023
Department Of Water Resources, Odisha plans to build an 18 MW (2x4 +2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village in the Nabarangpur district of Odisha. AFC India Ltd has completed the preparation of the SIA report. WAPCOS has prepared the DPR. EC for the project has been approved by the MoEF. The forest clearance stage -1 and stage 2 have been approved by the DFO. Construction of the approach road has been completed. The interstate boundary issue with Chhattisgarh state has been resolved. The civil works contractors Patel Engineering have started the boarding works of HRT. Civil works (Lot-2) contractor HES Infra. has completed the mobilization of equipment and construction works are yet to begin. Pre-bid has been completed for the hydro-mechanical works and its technical bid evaluation is in progress. Preparation of tender is in progress for the electromechanical works and its specification finalization has been completed. Further bids are expected soon. The project requirement is a load cum excavator, hydraulic excavator, dumpers, jackhammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, flap gates, Francis turbine, alternator, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, protection relays, transformer, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear, cables, nozzles, among others.
15/09/2022
Water Department of Odisha's offshoot, Kalahandi Investigation Division, has selected AFC India Limited as an SIA consultant to carry out socio-economic environmental studies for an 18 MW (2x4 2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village in the Nabarangpur district of Odisha. WAPCOS has prepared the DPR. SIA studies were completed by the consultant and it was approved. The collection of three-season baseline data and the hydrology report was accorded by the CWC. Preparation EIA /EMP report was completed. The forest clearance was accorded by the DFO for the diversion of forest land. Drilling and drifting works were completed.DPR was completed and it was approved by the CEA.GSI has approved the seismological report. Construction of the approach road has been completed. The project envisages the construction of an 87 m high and 3682 m long earthen dam across the Tel river. The interstate boundary with Chhattisgarh state is a major issue in the project. After several meetings, the issue has been resolved. The civil works contractors Patel Engineering have completed the mobilization of equipment at the site. Civil works package Lot-2 was awarded to HES Infra. and in the same package Gamon Infra. and Simplex Infra. are major contenders in price bids. Preparation of tender is in progress for the hydromechanical works and its specification is yet to be completed. Further bids are expected soon. The project requirement are load cum excavator, hydraulic excavator, dumpers, jack hammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, DG sets, bending and cutting machine, fuel/water tankers, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, actuation system, flap gates, Francis turbine, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, generator and its control panel, guide bearings, protection relays, transformer and its auxiliaries, lightning arrester panels, excitation system and its auxiliaries, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear and its auxiliaries - circuit breakers, isolators, capacitor bank, dis-connectors, governor panel, cables, transmission lines, nozzles, among others.
28/05/2022
Water Department of Odisha's offshoot, Kalahandi Investigation Division, has selected AFC India Limited as an SIA consultant to carry out socio-economic environmental studies for an 18 MW (2x4 2x5 MW) greenfield multi-purpose hydroelectric project located at Karlaparahi village in the Nabarangpur district of Odisha. WAPCOS has been selected as the DPR consultant.SIA studies were completed by the consultant and it was approved. The collection of three-season baseline data and the hydrology report was accorded by the CWC. Preparation EIA /EMP report was completed.TOR has been granted in October 2018. The forest clearance was accorded by the DFO for the diversion of forest land. Drilling and drifting works were completed.DPR was completed and it was approved by the CEA.GSI has approved the seismological report. Construction of the approach road is in progress and it is in the final stage of completion. The project envisages the construction of an 87 m high and 3682 m long earthen dam across the Tel river. The interstate boundary with Chhattisgarh state is a major issue in the project. Several meetings have been conducted to resolve the issue. The civil works contractors Patel Engineering has started the mobilization of equipment at the site. Pre-bid meetings are yet to conduct for the civil works package (lot-2). Preparation of tender is yet to start for the hydromechanical package and its specification is yet to be complete. Further bids are expected soon. The project requirement are load cum excavator, hydraulic excavator, dumpers, jack hammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, DG sets, bending and cutting machine, fuel/water tankers, EOT crane, mobile crane, air compressor, tunnel boring machine, dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, actuation system, flap gates, Francis turbine, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, generator and its control panel, guide bearings, protection relays, transformer and its auxiliaries, lightning arrester panels, excitation system and its auxiliaries, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear and its auxiliaries - circuit breakers, isolators, capacitor bank, dis-connectors, governor panel, cables, transmission lines, nozzles, among others.