Purthi Greenfield Hydroelectric Project   
Project Code 6000006179
Project Name Purthi Greenfield Hydroelectric Project
Project Type Capital Project Status Active
Sector Power Project Stage Engineering
Project Cost Rs. 2,020.26 Cr.  Project Phase Basic Engineering
NIC Subcode(s) Description
35101 Electric power generation by hydroelectric power plants
Facility Name Purthi Greenfield Hydroelectric Project Status Planning 
Sector Power Main Energy Source  
Commissioning Date   Other Energy Sources  
Address Purthi village (Dam-toe surface powerhouse) Shanan,
Chamba, Himachal Pradesh
171006, India
Telephone 02660-201204
Fax -
Owner Satluj Jal Vidyut Nigam Limited Satluj Jal Vidyut Nigam Limited Website http://www.sjvn.nic.in
Operator Satluj Jal Vidyut Nigam Limited Satluj Jal Vidyut Nigam Limited Website http://www.sjvn.nic.in

SJVN Ltd. plans to develop a 232 MW greenfield hydroelectric plant in the village of Purthi, District- Chamba, Himachal Pradesh. WAPCOS Ltd. is preparing the DPR of the project. Mantec Consultants is preparing an EIA / EMP report for the project. The hydrology report of the project has been approved by the CWC. Detailed design and drawing of the civil, hydro-mechanical, and electro-mechanical works have been completed. Drilling and drifting works have been completed. The geotechnical investigation and topographical survey report have been approved by the GSI. Forest clearance stage 1 is pending at the DFO. The approach road construction is in progress slowly due to the unfavorable weather condition. WAPCOS has been selected as the PMC of the project. Preparation of tender is yet to be started for the civil works package. Further bids are expected soon. The project requirements are: load cum excavator, hydraulic excavator, dumpers, jack hammer, water sprinkler machine, aggregate crushing plant, grouting pump, needle vibrator, air water jet blaster, drilling machines, DG sets, bending and cutting machine, fuel/water tankers, EOT crane, mobile crane, air compressor, tunnel boring machine (TBM), dozers, piles, elevators, building supports, gantry crane, spillway radial gates and hydraulic hoists, spillway stop logs, discharge pipe, valves, main inlet, intake trash rack, intake fixed wheel gates, desilting chamber gate, surge shaft gates, draft tube gate, trash rack cleaning machine, sluice gates, penstock, actuation system, flap gates, Pelton turbine, pumps, spiral, casing, runner blades, guide vanes, oil pressure unit, water seal and air seal, generator and its control panel, guide bearings, protection relays, transformer and its auxiliaries, lightning arrester panels, excitation system and its auxiliaries, battery bank, SCADA, unit control board, sensors, console, display panels, gas insulated switch-gear and its auxiliaries, governor panel, cables, transmission lines, nozzles, among others.

RFQ for the civil works package is likely to be floated in Q2 2023.

Expenditure Approval RFQ Date Release Date Start Date Completion Date Audit Date
2021 Q2:2023 Q2:2023 2023 2028 08/Sep/2023
Sell Electricity?
Name Project Role Designation Company City Phone Audit Date E-mail
Mr.Ravi Uppal Owner AGM Satluj Jal Vidyut Nigam Limited Satluj Jal Vidyut Nigam Limited Kinnaur 0177 - 2660180 02/07/2024 sjvn.ecfc@gmail.com
Mr.Vikash Mahajan Owner Additional General Manager Satluj Jal Vidyut Nigam Limited Satluj Jal Vidyut Nigam Limited Shimla* 01782 - 222030 10/10/2023
Equipments
Requirement Name Additional Details
Utilities
Turbine
Transportation
Structural
Storage
Sealing
Pumps
Process
Piping
Mechanical
Lubrication
Insulation/coating
Instrumentation
HVAC
Generator
Fire-proofing
Environmental
Electrical
Control Room
Communications
Civil
Auxiliary Equipment