Kotli Bhel Greenfield Hydroelectric Project Stage-IA   
Project Code 6000005376
Project Name Kotli Bhel Greenfield Hydroelectric Project Stage-IA
Project Type Capital Project Status Active
Sector Power Project Stage Engineering
Project Cost Rs. 2,074.02 Cr.  Project Phase Stimulation Studies
NIC Subcode(s) Description
35101 Electric power generation by hydroelectric power plants
Facility Name Kotli Bhel Hydroelectric Project Stage-IA Status Planning 
Sector Power Main Energy Source Water  
Commissioning Date   Other Energy Sources Diesel, Fuel Oil  
Address Kotli Bhel Hydroelectric Project Stage-IA, Village Muneth near Dev Prayag,
Tehri, Uttarakhand
249301, India
Telephone 01378-276100
Fax -
Owner National Hydroelectric Power Corporation Limited National Hydroelectric Power Corporation Limited Website http://www.nhpcindia.com
Operator National Hydroelectric Power Corporation Limited National Hydroelectric Power Corporation Limited Website http://www.nhpcindia.com

National Hydroelectric Power Corporation Ltd. (NHPC) plans to develop a 195 MW (3x65 MW) Greenfield hydropower project located in Tehri Garhwal District of Uttarakhand. The DPR has been approved by the CEA. EIA/EMP report have been approved. EC is yet to be granted by the MoEF. Forest clearance stage -2 is pending at the DFO. Construction of the approach road has been completed. Aquagreen Engineering Management Pvt. Ltd. has been selected as a PMC for the project. Preparation of the tender is in progress for the civil and hydro-mechanical works and its specification has been finalized. Further bids are expected soon. The major requirement will be three vertical Francis turbines, turbine-generator (alternator), station transformers, generator transformer, dumpers/loaders, excavators, TBM (tunnel boring machine), raise boring machine, unit auxiliary transformers (UAT), air compressor, digital governor, trash rack, main inlet valve (MIV), butterfly valve, non-return valve, radial gates, vertical lift gates, steel-lined penstock, EOT crane, transmission towers, power cables, monitor and monitor control unit, computerized control system, fireproofing system (Mulsifyer System, sprinkler system, etc), forced air circulation system (ID fans, blower, etc) among others.

RFQ for the civil and HM work is likely to be floated in Q4 2023

Expenditure Approval RFQ Date Release Date Start Date Completion Date Audit Date
Q3:2019 Q4:2023 Q4:2023 2024 2028 17/Nov/2023
Sell Electricity?
Buy Fuel? Fuel Name Diesel
Name Project Role Designation Company City Phone Audit Date E-mail
Mr.Satish Kumar Owner Chief Engineer National Hydroelectric Power Corporation Limited National Hydroelectric Power Corporation Limited Tehri 0137 - 276150 17/11/2023
Mr.Hemant Mishra Owner Sr. Manager (Contracts) National Hydroelectric Power Corporation Limited National Hydroelectric Power Corporation Limited Tehri 8191905180 25/11/2024 kotlibhelprojects@gmail.com
Equipments
Requirement Name Additional Details
Compresssors
  • Air Compressor
  • Rotary Compressor
  • Reciprocating Compressor
Valves
  • Gate Valve
  • Throttle Valve
  • Safety Relief Valve
  • Rotary Valve
  • Non-Return Valve
Turbine
  • Francis Turbine
Transportation
  • Truck
  • Pipeline
Pumps
  • Centrifugal Pump
  • Vacuum Pump
  • Sump Pump
  • Suction Pump
  • Submersible Pump
  • Rotary Pump
  • Reciprocating Pump
Piping
  • Pipe
Instrumentation
  • SCADA
  • PLC
  • Detectors
  • DCS
  • Tachometer
Generator
Electrical
  • Powerhouse
  • Transformer
  • Transmission
  • Switchyard
  • Substations
Control Room
  • Display Panel
  • Alarms/trips/interlocks
Civil
  • Underground Piping
  • Earthwork
  • Drilling
  • Boring
  • Tunnels
  • Surveying
  • Roads
Utilities
Structural
Storage
Sealing
Process
Mechanical
Lubrication
Insulation/coating
HVAC
Heat transfer
Environmental
Communications
Boiler
Auxiliary Equipment

Engineering Services
  • Civil
  • Electrical
  • Mechanical
  • Structural
Contracting Services
  • Civil
  • Electrical
  • Mechanical
  • Instrumentation